November 9, 2026
Don Snaman, Project Manager
675 Seaport Boulevard
Redwood City, CA 94063
Via email: c-dsnaman@redwoodcityport.com
cc:
Kristine Zortman, Port Executive Director
Port Commission
Keith Lichten, CA State Water Resources Control Board
Joseph Terry, U.S. Fish and Wildlife Service
Jana Affonso, U.S. Fish and Wildlife Service
Tami Schane, Department of Fish and Wildlife
Garrett Allen, Department of Fish and Wildlife
John Krause, Department of Fish and Wildlife
Justin Ly, National Oceanic and Atmospheric Administration
Katerina Galacatos, U.S. Army Corps of Engineers
Julie Beagle, U.S. Army Corps of Engineers
Valiela Luisa, U.S. Environmental Protection Agency
RE: September 2026 Ferry Terminal Project Draft Environmental Impact Report, Port of Redwood City
Dear Mr. Snaman,
The Loma Prieta Chapter of the Sierra Club, Citizens Committee to Complete the Refuge, Green Foothills, and the San Mateo County Bird Alliance respectfully submit the following comments regarding the Draft Environmental Impact Report (DEIR) for the Port of Redwood City Ferry Terminal Project. Our organizations have a deep interest in the San Francisco Bay and its ecosystems, as well as areas near the Bay where development may impact natural resources and climate resilience in the region. Together, we represent tens of thousands of Bay Area residents with a vested interest in the health and preservation of the San Francisco Bay and its ecosystems, and recognize the integral role they play in our defense against the threats of sea level rise.
Please note that we are also submitting a separate technical comment letter on biological resources, which we ask the Port to consider in addition to this letter.
The comments below demonstrate our concern that multiple sections of the DEIR analysis make impact findings that depend on data that has not been collected. The record does not contain sufficient project-specific information for meaningful public evaluation of the DEIR’s findings or to support enforceable, effective mitigation. Due to significant deficiencies in the CEQA required identification, analysis and mitigation of impacts, as noted in both the comments below and our companion letter on biological resources, we believe the inadequacy of the DEIR must be rectified and the Port, as lead agency, must provide the public and agencies an opportunity to review and provide comments on a recirculated DEIR before a Final EIR is released and certified.
Our comments are organized into three categories:
Overarching comments that cut-across multiple issue areas,
Specific comments related to CEQA analysis and mitigation categories, and
Policy issues that warrant consideration prior to project approval.
I. Overarching comments
A. The DEIR must explain its reliance on the 2003 Program EIR and demonstrate its continued applicability
The DEIR identifies the Redwood City–San Francisco ferry route as part of the regional ferry expansion identified in WETA’s 2002 Implementation and Operations Plan and its evaluation in the 2003 Program EIR. The DEIR also states that it carries forward Program EIR Mitigation Measure B-11 as MM BIO-11. CEQA permits reliance on prior programmatic review where its analysis remains applicable, and the DEIR includes some new project-specific analyses. However, the Port should identify which prior assumptions, analyses or mitigation measures it relies on, explain why they remain applicable, and support that conclusion with current, project-specific information.
The 2003 Program EIR is more than two decades old and preceded the current terminal design, the two proposed routes and vessel assumptions, the present service expansion assumptions, and current information on sea-level rise and shoreline conditions. It cannot substitute for current analysis where project details, environmental conditions, or available wildlife information have changed. The Port should identify what specific elements of the 2003 analysis is carried forward, what has been updated, and where current evidence supports the continued adequacy of MM BIO-11 and other measures. (DEIR Sections 2.2, 3.3.5.3.3, 3.9; Appendix G; CEQA Guidelines §§ 15162, 15168(c).)
As discussed in our companion letter on Biological Resources, this issue is directly relevant to whale and waterbird impacts. The DEIR finds that frequent ferry operations are likely to cause additional disturbance and avoidance of otherwise suitable foraging habitat, a significant effect before mitigation. Yet MM BIO-11, carried forward from 2003, says only to consolidate routes in common corridors, use deeper channels where possible, and minimize crossings of shallow areas. The DEIR should explain, using current route-specific wildlife and vessel information, how this measure reduces the identified disturbance to less than significant under current conditions. The measure does not specify a service schedule, disturbance threshold, monitoring protocol, adaptive response, or other performance standard that demonstrates that result.
Requested action OA-1. Identify the specific portions of the 2003 Program EIR and mitigation measures relied on for this project, explain why their assumptions remain applicable, and provide current project-specific analysis where the earlier review does not address current effects.
B. The DEIR must support its impact findings with current, project-specific analysis
Across geology, hazards, and hydrology, the DEIR sometimes identifies further site investigation or final-design work while reaching a less-than-significant conclusion now. CEQA permits deferral of mitigation details only where the agency commits to mitigation, adopts specific performance standards, and commits to later development of details consistent with those standards. (CEQA Guidelines §15126.4(a)(1)(B).) General references to later studies, permits, or standard practices do not by themselves explain how an identified effect will be avoided or reduced.
For each deferred investigation on which a finding depends, the DEIR should identify the possible results, explain whether they could change the significance conclusion or the project design, and specify what enforceable response will apply if testing identifies a more serious condition. Where a later result could require a different dredging or disposal method, slope treatment, ground improvement, or mitigation, the EIR should analyze the reasonably foreseeable effects of that response or explain how the issue will receive additional CEQA review before the related work is approved.
Requested action OA-2. Revise the affected analyses to disclose the material uncertainties, their implications for each significance finding, and the binding performance standards and response measures that will apply if the DEIR assumptions are not confirmed.
II. Environmental Impact Analysis and Mitigation Categories
Air Quality (3.2) and Greenhouse Gases (3.7)
Operational vessel emissions and feasible mitigation
The DEIR identifies the nitrogen oxide (NOx) emissions generated by running the passenger ferries as significant and unavoidable. The report notes that no feasible mobile-source mitigation currently exists to completely offset these operational emissions. Because the planned long-distance routes make fully zero-emission electric boats unfeasible for the immediate future, the project relies on current “renewable diesel”1 vessels until they reach the end of their service life, which is assumed to be 25 years.
The conclusion that zero-emission vessels are not currently feasible does not resolve whether other feasible measures could reduce NOx before fleet replacement or whether a feasible alternative could serve some or all of the routes. The DEIR should disclose the feasible mitigation measures considered, explain why measures not adopted are infeasible or ineffective, and evaluate enforceable near-term steps such as cleaner fuels and operating practices.
If operating the proposed ferries at 7 knots for extended durations within the Redwood Creek channel could alter the engine load factor or change the ratio of particulate matter and NOx emissions, emissions inventory calculations for the duration of the low-speed transit through the channel should be disclosed and localized impacts addressed. Additionally, shore power for vessel hotel loads should not be treated as zero-emission unless the analysis supports that conclusion.
The DEIR should clearly connect its emissions inventory and mitigation review to the same vessel activity, route, speed, and service assumptions used in the project description, including the potential 20 percent increase in service. (DEIR Section 3.2 and Appendix B.)
Requested action AQ-1. Reconcile the emissions inventory with project service assumptions, disclose feasible mitigations considered and any technically feasible zero-emission alternative, including postponing commencement of service.
GHG reduction depends on assumed diversion only from solo driving
The DEIR concludes that the project would reduce operational GHG emissions by 4,365 metric tons of CO2e per year, with 10,974 metric tons from ferry service offset by 16,046 metric tons from on-road vehicles. That result depends on treating every end-to-end trip avoided between Redwood City and San Francisco or Oakland as a drive-alone trip. The transportation analysis does not estimate how many ferry riders would otherwise drive alone, carpool, or use existing transit; it applies existing mode shares to first- and last-mile access trips, while assuming all avoided end-to-end trips would be solo driving. (DEIR § 3.7.5.1.1, pp. 3.7-27–28, Table 3.7-6; § 3.14.5.2.1, pp. 3.14-39–44, Tables 3.14-7, 3.14-10, and 3.14-11; Appendix H, § 2.2, pp. 2-19–21.)
This assumption may overstate avoided auto travel and GHG emissions if some ferry riders would otherwise use Caltrain, SamTrans, carpools, or other modes. The DEIR identifies existing Caltrain shuttles as a potential connection to the terminal, but should clarify whether any added shuttle service and its VMT and emissions are included in the analysis. The DEIR also assumes diesel vessels over the project life for its emissions analysis, while anticipating replacement with zero-emission vessels at or within approximately 25 years; it does not identify a project-specific enforceable transition schedule. (DEIR § 3.7.5.1.1, pp. 3.7-28–29; § 3.14.5.1.1.1, pp. 3.14-29–30; Appendix H, § 2.2, pp. 2-20–21.)
Requested action GHG-1. Substantiate the assumed shift from only drive-alone trips or revise the analysis to reflect plausible diversion from solo driving, carpools, and existing transit, including electrified Caltrain. Identify and include any incremental shuttle VMT and emissions, clarify the enforceable vessel and fuel assumptions, and report the resulting net GHG emissions under reasonable scenarios. Revise the significance conclusion if the claimed net reduction is not supported.
Geology and Soils (3.6)
We have multiple concerns regarding the sufficiency of analysis methods and impact conclusions for Section 3.6 Geology, Soils, and Paleontological Resources. These same concerns also apply to Section 3.9 Hydrology and Water Quality.
The DEIR identifies high liquefaction susceptibility, settlement, lateral spreading, and potential movement of the shoreline slope. However, the analysis lacks technical field studies of the actual Project site, instead referencing documents that are local or regional but not specific for the Project site. One exception is the Geotechnical Desktop Study2 prepared for the Port of Redwood City in 2024, which draws on previous, offsite investigations. The Study covers only the onshore portion of the project. No equivalent in-water study of offshore components of the Project is provided.
As a “Desktop” study it is a review of available literature performed by topic-qualified staff. It does not include any new on-site field work on land or in-water. However, the Study does identify limits in the available data and recommends and describes additional on-site technical investigations that are needed for the Project proposed. None of those studies occurred prior to preparation of this DEIR. The DEIR repeatedly relies on future site-specific investigations to determine foundation, ground-improvement, fill, and slope measures while concluding that seismic-related impacts would be less than significant. (DEIR § 3.6, pp. 3.6-15–18; Appendix E.)
Similarly, in 3.6.2, Methodology, the DEIR states: ”For the purposes of the environmental analysis, the proposed project is assumed to comply with existing regulatory controls” (emphasis added). As the DEIR has analyzed only a preliminary diagram in place of a design and proposes providing a final design project to regulators, the public and decision makers have insufficient information to know what actions the Project will or won’t take nor what at-risk subsurface conditions may be identified in post-CEQA geotechnical analysis.
The EIR should explain how the recommended investigations relate to the conclusions for liquefaction, settlement, and slope stability, and whether the range of possible findings could require improved subsurface, surficial and shoreline characterization beyond what is analyzed in the DEIR. If code compliance and later engineering are the basis for the findings, the EIR should identify the standards that govern the design and explain why they ensure that the environmental effects of the reasonably foreseeable design measures will be less than significant. This is especially important where those measures could change grading, construction methods, or disturbance near the shoreline.
We refer you to the following recommendations from the Geotechnical Desktop Study. (Ed Note: emphasis added)
“3.2 Soil Engineering Properties
Engineering properties of each soil strata from the 2012 Report should be utilized for preliminary design only for the onshore portion of the Project Site due to the following considerations:
› The engineering properties of fill can vary significantly due to differences in the fill source, placement method, as well as compaction effort.
› Limited number of tests were performed for undocumented fill with only one standard penetration test and one undrained shear strength test conducted.
› Detailed seismic hazard reviews with adequate site-specific data is needed.
Given the Project Site's high seismicity (see Section 4 below), a thorough seismic hazard review with adequate site-specific data is essential. Anticipated strong ground shaking from nearby faults and associated seismic hazards, such as liquefaction-induced settlement, cyclic densification, lateral spreading, and seismic movement of shoreline slope, necessitate careful consideration and review.
› The long-term consolidation behavior of the compressible Bay Mud is critical for the proposed development's performance. Excessive consolidation could adversely impact the pavement, grading, drainage and foundation system.
Therefore, site-specific soil sampling and testing for Bay Mud are recommended to ensure the long-term functionality of the onshore portion of the Project Site.”3
“6 Conclusions and Recommendations
The 2012 Report for the Wharves 1 & 2 Replacement Project provides information on the subsurface conditions that are likely relevant to the Project Site. Conclusions regarding seismic hazards and other geotechnical hazards are summarized in Sections 6.1 and 6.2, respectively. Note that the conclusions are based on the 2012 Report and are provided for reference only. The actual seismic/geotechnical hazards or other unknown hazards at the onshore portion of the Project Site may differ and should be re-assessed with a site-specific geotechnical investigation.The site-specific geotechnical investigations in Section 6.3 are recommended to evaluate/confirm the potential seismic/geotechnical hazards and ensure the successful development of the onshore portion of the Project Site” (emphasis added).4
“6.3 Recommendations for Site-Specific Geotechnical Investigations
For the Project Site, the following site-specific geotechnical investigations are recommended:
› Additional Boreholes: additional borehole(s) to be drilled and terminated atminimum 100 feet with soil sampling across the Project Site to confirmsubsurface conditions.
› In-Situ Testing: Conducting Standard Penetration Tests (SPT) and/or ConePenetration Tests (CPT) in the new boreholes.
› Groundwater Monitoring: Installing piezometers to monitor groundwater levelsat the Project Site.
› Laboratory Testing: Performing laboratory tests on soil samples from the new boreholes, including grain size distribution, Atterberg limits, moisture content, compaction test, expansion index, shear strength, and consolidation tests, etc.
When applicable, perform necessary tests on new fills, such as a compaction test, etc. for roadway design.”5
Requested action GEO-1. Provide site-specific evidence, as recommended in the Desk Study, to support each geology and soils significance finding, or analyze the reasonably foreseeable design response to future field investigations and its environmental effects, identifying enforceable standards where mitigation is necessary; and revise and recirculate Sections 3.6, 3.8, 3.9, 3.3, and others in which analysis is affected, for full public review.
Given that the Geotechnical Desktop Study excluded the Project’s shoreline and offshore locations (near-shore dredging, sediment contamination, pile driving, Shell Unloading Wharf demolition, seismic and erosion vulnerability of shorelines), impact analysis cannot be accurate nor adequate in Section 3.6 or other Sections due to a lack of investigations and findings at offshore locations of the Project e.g., Ferry terminal dredging and Shell Unloading Wharf demolition.
Requested action GEO-2. Acquire technically qualified recommendations to identify all shoreline and offshore investigations needed to provide site-specific geologic, hydrologic, and contaminant data; have those investigations performed with reports generated; and revise and recirculate Sections 3.6, 3.8, 3.9, 3.3, and others in which analysis is affected, for full public review.
Hazards and Hazardous Materials (3.8)
Mitigation HAZ-1 is inadequate to protect the environment from contaminants released during offshore construction and demolition activities
Impact 3.8.2 evaluates whether the project would “create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment.” The DEIR (page 3.8-23) concludes that, because sediment samples from the vicinity of Port of Redwood City wharfs 1 through 4 and a proposed multi-use basin were found to be acceptable for disposal or beneficial use6, sediments dredged for construction of the Ferry Wharf or disturbed during pile driving will likewise be non-hazardous.
This conclusion is not supported by any relevant data. As discussed in detail in our joint letter on Biological Resources, the 2024 sediment samples were collected from near the active wharfs, areas that are dredged on a frequent basis. It is unlikely that sediments along the project shoreline have ever been dredged or tested; the composition of those sediments is unknown. The mitigation measures proposed for dredging (MM-BIO-4) do not include any engineering solutions that would prevent suspended sediments from migrating away from the dredging site and impacting biological resources. Thus, the conclusion that HAZ-1 will reduce Impact 3.8.2 to Less than Significant for dredging and pile driving is unwarranted.
Requested action HAZ-1. Sampling and analysis of sediments in the proposed wharf area is needed to determine environmental impact. The analyses should include all parameters required for comparison with RWQCB disposal and beneficial reuse acceptance criteria, including aquatic and benthic toxicity tests. Without these data, regulators and the public have insufficient basis to comment on the adequacy of the current DEIR. The reissued DEIR should not assume that sediments will meet acceptance criteria; rather, it should describe steps to be taken in the event that the sediments are found not suitable.
No sediment sampling has occurred in the Shell Wharf area; thus, it is unknown whether impacts to the environment from sediment disturbance during demolition will be significant.
Requested action HAZ-2. Sampling and analysis of sediments in the proposed wharf area is needed to determine environmental impact. The analyses should include all parameters required for comparison with RWQCB disposal and beneficial reuse acceptance criteria, including aquatic and benthic toxicity tests. Without these data, regulators and the public have insufficient basis to comment on the adequacy of the current DEIR. The reissued DEIR should not assume that sediments will meet acceptance criteria; rather, it should describe steps to be taken in the event that the sediments are found not suitable.
The EIR should propose mitigations to avoid harm to the environment during demolition, which should include measures for both a non-hazardous and a hazardous sediment designation.
Mitigation HAZ-1 is inadequate to protect construction workers, the public, and the environment from exposure to toxic chemicals released during site preparation, import of fill soil, and pile driving
The DEIR does not specify any measures to protect construction workers, the public or the environment from exposure to toxic chemicals released during dust-generating activities such as site leveling, fill dumping, and on-land pile driving. The emissions calculations for construction activities (Appendix B.2) and the health risk assessment consider only criteria pollutants and reactive organic gases (ROG) from diesel exhaust.
Although no hazardous waste sites have been identified within or immediately adjacent to the Ferry area, there is a potential for surface soil contamination associated with past operations at the Sims Metal scrap metal recycling facility, located 0.3 miles to the southwest. The DTSC identified concerns with releases of Light Fibrous Material (LFM), a byproduct of metal shredding that can contain toxic levels of heavy metals and other hazardous materials.7 In addition, there have been multiple fires at the Sims Metal facility, including one in 2024 that spread a large smoke plume over Santa Clara County.8 In addition to heavy metals, car and shredding waste fires can generate products of incomplete combustion (PICs) that include polycyclic aromatic hydrocarbons (PAHs), polychlorinated dibenzodioxins/furans (PCDDs/PCDFs), polyfluorinated alkyl substances (PFAS) and other persistent toxic contaminants. These chemicals adhere to soil particles and could pose a human health and ecological risk from exposure to contaminated dust.
Requested action HAZ-3. Require that no earth-moving or on-land pile driving activities take place until a representative number of surface soil samples are tested for metals, asbestos, and the PICs listed above. After agency and public review of the soil testing report and approval of the report by regulatory agencies, the soil concentrations should be combined with estimated PM2.5 emissions to model human and ecological receptor exposures and health risks from airborne dust transport and deposition in a Soil Management Report.
Ferry area: the DEIR (page 3.8-22) states “...if contaminated soils are present, these soils would be covered with new, clean fill and would not be disturbed during construction.”
Requested action HAZ-4. Explain how the large piles of concrete and rip-rap, 30-foot-high piles of aggregate and other debris that currently cover the project site will be converted to a clean, level soil surface without generating dust.
If it is anticipated that the site will be cleared and leveled by the Port before starting the project, will there be a separate site investigation and health risk assessment associated with those actions?
Requested action HAZ-5. Explain how thousands of truckloads of fill will be dumped and graded without raising any dust from the surface soil.
Visitor Serving Area: Unlike for the Ferry Area, there is a requirement to perform a Phase II Environmental Site Assessment and Soil Management Plan prior to starting site work, and to prepare a Soil Management Plan and health risk assessment. However, the DEIR discusses only a soil investigation and mitigation measures for volatile organic chemicals (VOCs) associated with historical diesel fuel contamination within the visitor-serving areas (page 3.8-27).
Requested action HAZ-6. Since there is no commitment to prepare a supplemental EIR for the visitor serving area, provide more detail on the sampling requirements, decision criteria, and mitigation measures for non-VOC toxic contaminants.
Hydrology and Water Quality (3.9)
Omissions and Corrections
Please address the following omissions and corrections, identified below by DEIR section headings.
1. Section 3.9.2 Methodology
The discussion cites a suite of maps and documents reviewed for impact analysis. It omits several relevant sources.
BCDC: Adapting to Rising Tides, a web compilation of shoreline analysis mapping tools: https://www.adaptingtorisingtides.org/project/regional-sea-level-rise-mapping-and-shoreline-analysis/
San Francisco Estuary Institute, San Francisco Bay Sea Level Rise Adaptation Atlas, 2019 and associated resources: https://www.sfei.org/projects/san-francisco-bay-shoreline-adaptation-atlas
2. Section 3.9.3 Regulatory
Section 3.9.3.1.2 State
Water Quality Control Plan for the San Francisco Bay Basin
Table 3.9.1 - Marine Water Quality Objectives for Toxic Pollutants for Surface Waters is missing the numerical criterion for copper in the South Bay9, although that is cited in the text on page 3.9-10. Please reconcile the table with the text.
3. California Sea Level Rise Planning and Adaptation
Section 3.9.3.1, Regulatory Setting, provides a confusing and misleading discussion about the Bay Conservation and Development Commission (BCDC) and its regulatory role. Within a lengthy list of State regulatory requirements and agencies, the DEIR includes this discussion on p.3.9-16 regarding the 2023 legislation, SB272: “These Sections require local governments within the coastal zone, including the jurisdiction of the San Francisco BCDC, to develop a sea level rise plan.” This discussion does not mention State regulatory responsibility assigned to BCDC by SB272.
Section 3.9.3.1.3 Regional/Local
The DEIR lists: “San Francisco Bay Conservation and Development Commission and McAteer-Petris Act “ as applicable regulations.
BCDC is a State agency that holds regulatory jurisdiction for all cities and counties adjoining San Francisco Bay with multiple regulatory responsibilities assigned by the State, including regulatory responsibilities assigned by SB272 and omitted in 3.9.3.1.2. SB272 states the following.
“Section 30985 (a) A local government lying, in whole or part, within the coastal zone or within the jurisdiction of the San Francisco Bay Conservation and Development Commission shall develop a sea level rise plan as part of either of the following as applicable
(2) A subregional San Francisco Bay shoreline resiliency plan that is subject to approval by the San Francisco Bay Conservation and Development Commission consistent with the guidelines established to subdivision (b) of Section 30985.2.”
“Section 30985.5. Local governments that secure approval from the California Coastal Commission or the San Francisco Bay Conservation and Development Commission, as applicable, under subdivision (a) of Section 30985 shall receive priority consideration for funding, subject to Legislative appropriation, to implement sea level rise adaptation strategies and proposed projects within the municipality's approved sea level rise plan.”
Taken together, BCDC has a regulatory role in guiding and approving the Regional Shoreline Adaptation Plans for every Bay jurisdiction per legislation approved in 2023 and the RSAP Framework the agency finalized in December 2024. Prior to those dates, Redwood City completed its Sea Level Rise Study. Findings of adaptation action of that study may be useful during development of the City’s RSAP inclusive of this Project site and to meet standards BCDC identifies in its 2024 Guidelines.
Please revise the DEIR sections cited above to (1) clarify the BCDC jurisdiction and regulatory actions under SB272, (2) identify BCDC as a State agency and the McAteer-Petris Act as State law and (3) include all SLR and regulatory discussion about BCDC in one section.
Section 3.9.3.2 Environmental Setting inadequately describes background and conditions, particularly in regards to marine soils where the Project proposes to disturb soils by dredging or demolition
The section fails to describe the history of the Port, its operations dating to 1878 and commercial uses involving a wide range of activities throughout its environs. Through time, untold hundreds of ships berthed at its wharfs, loaded and unloaded an extensive array of materials and, on occasion, spillage occurred. Likewise, ship operators used time at docks to repair leaks in the vessels, another potential source of spillage.These spills would have contaminated soils directly adjoining the shoreline and, from wharf to wharf, contamination conditions vary with the spillage history at the location.
The DEIR cites a 2024 report by Haley and Aldrich as a water quality reference regarding sediment content. The analysis derives from studies done at the sites of Wharf 1 and Wharf 4 and was unrelated to the Ferry Project. The DEIR intention appears to be relying on the report’s data for water quality conclusions for in-water dredging and pile driving required to build the Ferry Terminal and do so without performing any Project-site-specific analysis. This is inadequate for the environmental analysis needed. (Please see Overarching Comment B above.)
10
Sediments at the Ferry Terminal site may be unlike those at the Wharf 1 and 4 locations due to distance and historical variation of location use. It is also a concern that the planned demolition of the Shell Unloading Wharf (SUW), which spans substantial length along the shore (~600’), is even greater distance from the referenced Wharfs. Those sediment conditions are unknown.
Requested action HWQ-1. Perform project-specific sediment analysis at both the Ferry Terminal and SUW sites and replace reliance on the Haley & Aldrich 2024 report with site-specific findings for each dredge and demolition location. Disclose applicable toxicity/acceptance criteria, and provide a response plan if results are unsuitable.
The Environmental Setting of Section 3.9 omits discussion of the existing site surface conditions, which include piles of concrete rubble and riprap, 30’ high piles of aggregate, and other debris. On page 3.8.22, the DEIR states “...if contaminated soils are present, these soils would be covered with new, clean fill and would not be disturbed during construction regarding the Ferry area.” The Project proposes to remove and level the materials but does not discuss mitigations to analyze for and take appropriate action to avoid water quality impacts, inclusive of removal and disposal methods. The Project proposes to cover contaminants with fill if found, without discussion of whether that action is the best mitigation to avoid impacts or if there is potential that buried contaminants may be transported by rising groundwater.
Requested action HWQ-2. Ensure that shallow groundwater investigations are used to identify any location where rising groundwater may transport contaminants.
Insufficient site-specific data on soil and groundwater conditions undermines transparency and significance findings
As described in section 3.6 of this letter, the Geotechnical Desktop Study identifies limitations in the available data and recommends and describes additional on-site technical investigations that are needed for the proposed Project. None of those studies occurred prior to preparation of this DEIR, leaving data gaps that undermine the public’s ability to assess the DEIR’s findings and conclusions.
Requested action HWQ-3. Provide site-specific evidence, as recommended in the Desk Study, to support each hydrology and soils significance finding or analyze the reasonably foreseeable design response to future field investigations and its environmental effects, identifying enforceable standards where mitigation is necessary; and revise and recirculate relevant DEIR Sections for full public review.
The DEIR concludes that adding seven feet of compacted soil to the site will remove future vulnerability to rising groundwater. However, the DEIR analysis does not appear to address groundwater rise conditions in the areas outside the raised development platform, including the setbacks along Westpoint Slough and Redwood Creek, the lower sections of the slope that bolster the edges of the platform, the site access road and the ferry boarding slope. Potential interaction of Project features with rising groundwater or changing tidal conditions could affect drainage, erosion, slope and shoreline performance, or the movement of contaminants in those areas. As the setback areas will be needed for future sea level rise infrastructure (levee, flood walls) and provide a public trail, failure to assess the shallow groundwater conditions on the site’s lowlands is inadequate for build-out of the Project.
Requested action HWQ-4. Clarify the data and analysis for low-lying areas outside the raised platform, including the shoreline setback, the lower reaches of the slopes, the access road, and the ferry boarding slope, where groundwater conditions could affect drainage, erosion, slope and shoreline stability, water quality, or contaminant transport. Show how the proposed grading and drainage perform under assumed sea level rise conditions. State the factual basis for any less-than-significant finding and thresholds at which future mitigation will be needed to prevent project-related drainage, erosion, slope, and water-quality effects.
Over-reliance on future design or permitting analysis throughout Section 3.9.5 Project Impacts (Impacts 3.9-1, 3.9-3, 3.9-4)
Comments here detail concerns spotlighted in our Overarching Concern B. The DEIR employs a concerning pattern of deferring impact analyses to post-CEQA technical studies.By deferring site-specific investigations to follow certification of the Final EIR, the Project denies the public the opportunity to be fully informed about impacts and to make informed comments, as CEQA requires.11 Furthermore, it leaves the lead agency with unsubstantiated findings on which to base Project approval and introduces the potential for risks of unknown impacts if the Project moves forward, if approved.
Requested action HWQ-5. For each water-quality finding of less than significant impact that depends on future design, BMPs, or permits, identify the potential impact(s), applicable enforceable requirement and explain how it supports the significance conclusion.
Section 3.9.5.3.1 Erosion and Siltation On- or Off-Site
1. This section does not discuss impacts of ferry operations and specifically the impact that will erode marshes of the Don Edwards San Francisco Bay National Wildlife Refuge (Bair Island and Greco Island).
Impact analysis of this Section omits analysis of wake erosion produced by ferry operation and a related mitigation measure.
Requested action HWQ-6. Please add a section that includes impact analysis of marsh erosion that includes the following:
Analysis of the cumulative marsh erosion impact resulting from eight or more daily ferry trips into and out of the port, alternately arriving and departing,
Analysis that addresses the cumulative sediment loss per day, and
Analysis that summarizes the impact per trip, per total daily trips, and identifies opportunities to mitigate perhaps through varied arrival and departure schedules.
The analysis should address the following:
Determine whether impacts differ between ferry arrivals and departures,
Assess whether the interval between one ferry’s arrival and another’s departure allows wake-related erosion to subside, or whether the effects may combine and prolong the erosion episode,
Quantify sediment loss and suspended sediment associated with vessel wakes, document physical changes to the marsh shoreline, and map the locations of affected marsh, and
Identify and analyze risks to wildlife, including erosion at harbor seal haul-outs.
Please see our companion letter about Biological Resources for more discussion on this issue.
2. The Project proposes to build the entire 7’ platform of compacted soils following grading of the site including both Ferry Terminal and Visitor-serving lands. It will then perform all other of the components for Ferry Terminal. In the meantime, it is expected that development of the Visitor-Serving area will not occur for an unknown period of time. Components of a stormwater management system will be installed. The DEIR states the compacted earth will be stabilized with weed free hydroseeding, vegetation, and erosion control materials such as geotextile mats.The DEIR provides no construction schedule i.e when any of this will done, in what order it will be done, nor information about the resistance of these stabilization methods to extreme weather events that have become more frequent due to climate change.
a. Can the stabilization methods resist and prevent erosion in the face of extreme storms (rain intensity, sea surge, high winds, serial storm events), extreme tide-height events (El Nino, Kelvin waves, King Tides) and major ground disturbing seismic events. How long will this compacted soil be without adequate erosion protection? Without stabilization, significant erosion could occur. Are vegetated slopes likely to erode to form channels transporting sediment. Will geotextile mats remain secure in high winds and atmospheric river downpours? Would extreme weather or seismic events also produce significant erosion impact?
b. The DEIR describes plans for but does not provide analysis of the adequacy of the storm water system to respond and mitigate extraordinary weather conditions ( listed above) and prevent overflow from the exposed, compacted soil platform and from new impervious surfaces (parking lot, access road) onto adjoining lands (roads, railways,waterways) and potential flow-transport of eroded soils offsite including offshore. What stormwater system capacity does a Bay-exposed site require?
Requested action HWQ-7. Provide detailed discussion of erosion prevention regarding ferry operations, 7’ compacted soil stabilization and stormwater system capacity during extreme weather and seismic events. Please also discuss erosion prevention methods in detail with options to best avoid erosion in the face of extreme storms or seismic events, incorporating the most suitable in appropriate mitigation measures.
Section 3.9.5.1 Would the proposed project violate any water quality standards or waste discharge requirements or otherwise substantially degrade surface or ground water quality?
DEIR p.3.9-32: “Sediment sampling and analysis has not been conducted at the ferry terminal proposed dredging area.”
The Project mentions it will need to dredge near the ferry terminal prior to construction and will perform maintenance dredging at that location, unrelated to the recurring U.S. Army Corps of Engineers maintenance dredging of the main Redwood Creek channel. However no detail of the ferry terminal dredging is provided nor identification of specific location. Further, demolition of the Shell Unloading Wharf is included with no methodology, leaving the reader unable to assess whether there will be substantial disturbance of shoreline-adjacent soils nor if it would require dredging if soils are contaminated. We find it impossible to accurately comment as the DEIR includes no detailed description of actions that will be taken nor of their duration. What equipment is used? Will noise or vibration be an impact? Will channel flow be interrupted or impeded during action? Will actions involve hazardous materials? Are wildlife or their habitats at risk? All of these impacts might be significant and require mitigation.
Requested action HWQ-8. Identify the enforceable water-quality conditions for recurring terminal dredging and demolition sediment disturbance. Explain how those actions and anticipated sediment results support the DEIR’s conclusions for each impact.
3.10 Land Use
Clarify shoreline work and development envelope
The DEIR describes a raised site, a 100-foot building setback, and a landscaped perimeter; it identifies a 2:1 slope and possible riprap at the slope base as a stabilization approach. These descriptions do not establish how the proposed grading, shoreline slope, public trail, wetlands, and development fit together or how much space remains for habitat and future shoreline adaptation. It should also clarify proposed fill areas of the existing shoreline. The EIR should provide representative cross-sections for the north, northwest, and west shorelines showing existing and proposed grades, tidal and wetland boundaries, the fill toe and crest, any riprap or retaining feature, the trail, and trail ramp, and the proposed buildings. It should quantify the limits of fill and work near tidal waters, wetlands, and BCDC jurisdiction.
The existing aerial view of the site (below) indicates the current edge of the usable site and the lower portions of the site along the shoreline that are currently subject to tidal action.
Above: Existing conditions showing the site and the current profile of the shoreline as well as the existing adjacent public park and Bay Trail along its shoreline.
“Project Site Plan” from Project Description, Figure 2-5
The site plan (above) and the rendering detail, below, suggest potential fill associated with a new retaining wall and Bay Trail extension that extends beyond the existing shoreline profile along the north, north-west and west edges of the Project site.
Detail of rendering above showing indication of a new retaining wall at shoreline fill area along the edge of the site
The Bay Trail Plan explicitly states that policies aim to locate the trail close to the shoreline but without requiring fill. An applicant must first prove that there is no feasible upland path or landward option before BCDC will consider allowing fill over wetlands.
Figure 2-5, above, from the Project Description appears to indicate that the extension of the Bay Trail will be along a new retaining wall constructed over wetlands. The two figures below show the Bay Trail extension alignment. The figure on the left, below, shows the proposed Ferry Project’s Bay Trail extension on the proposed Site Plan (Figure 2-5). The figure on the right shows where the Bay Trail extension may need to be located in order to avoid filling in the lower wetland parts of the shoreline currently subject to tidal action.
Bay Trail alignment along the shoreline as proposed (left) and shown relocated along the existing shoreline (right)
Requested action LU-1. Clarify the horizontal extent of fill area, if any, encroaching into or abutting existing marsh or wetlands along the North, Northwest, and West edges of the Project site.
Requested action LU-2. Provide shoreline cross-sections showing the existing grade and the proposed platform grade, proposed shoreline edge, the toe of the retaining wall, and the Bay Trail ramp to access the terminal site platform. Quantify the project footprint and fill limits so the public can evaluate the physical effects of the design actually proposed.
3.14 Transportation
Construction hauling and access
The DEIR estimates approximately 124,200 cubic yards of imported fill and up to 100 daily truck trips over approximately seven to nine months. It should clarify whether “trips” means one-way movements or round trips and identify the assumed fill source and haul distance, truck capacity, routes, work hours, hourly distribution, and overlap with other construction. The daily estimate alone does not show how frequently trucks would pass a location or whether peak periods could create queues, access delays, or safety conflicts. (DEIR Chapter 2; § 3.14; Appendices B and H.)
The FEIR should map the assumed haul route from the fill source to the project site, including whether trucks would be restricted to Seaport Boulevard, the Pacific Shores perimeter road, and the Woodside Road/US-101 interchange. It should evaluate truck volumes by hour, interaction with peak traffic, and any overlap with other reasonably foreseeable construction or interchange work. The analysis should also address whether hauling could affect emergency access. (DEIR § 3.14; Appendix H; Caltrans, District 4, “SR-84–U.S. 101 Interchange Reimagined.”)
The FEIR should identify whether East Bayshore Road or the frontage-road corridor between Marsh Road and Seaport Boulevard is a proposed or potential haul route, and map the route relative to nearby residences, mobile-home communities, and bicycle and pedestrian facilities. San Mateo County’s draft environmental justice appendix identifies its unincorporated Mobile Home Parks community as a High-Priority EJ Community and reports a 77th-percentile combined pollution-burden score for the associated census tract.12 Because the tract includes areas beyond the Parks, the FEIR should identify the residents and communities actually near any proposed route rather than rely on census-tract averages alone. (San Mateo County, Environmental Justice Communities Technical Appendix, Public Draft, February 2025, pp. 3, 8–11.)
If East Bayshore Road is proposed for hauling, evaluate potential exposure of nearby residents, including residents of Harbor Village and other mobile-home communities, to dust and diesel exhaust; truck conflicts at residential driveways and with people biking, walking, or using mobility devices; and pavement or subgrade damage, settlement, and vibration from repeated loaded trucks. The East Bayshore Road frontage corridor sits directly atop young Bay Mud. Because this underlying geological stratum has an incredibly high water content and low shear strength, it lacks the load-bearing capacity required for heavy traffic. Address concerns that the underlying geology makes it structurally ill-equipped to handle the weight.13
For each road segment on the haul route, including the Pacific Shores perimeter road, document pavement condition and load capacity. (DEIR §§ 3.2, 3.6, 3.11, and 3.14; Appendices B and H.)
Requested action TR-1. Identify the fill source and haul distance, define the truck-trip estimates, and map the haul route and hourly truck distribution. Analyze peak-period traffic, emergency access, and any reasonably foreseeable overlap with other construction at the Woodside Road/US-101 interchange. Adopt an enforceable haul-route plan that keeps loaded trucks on designated truck routes and primary arterials and excludes East Bayshore Road, the frontage-road corridor between Marsh Road and Seaport Boulevard. Document the pavement condition and load capacity of each route segment, and establish enforceable inspection and repair obligations for project-caused damage. If the Port proposes using the East Bayshore corridor, provide route-specific analysis of air quality, residential access, bicycle and pedestrian safety, and noise and vibration, and adopt measures to address any significant effects.
Emergency access claims and alternatives
The Port is identified in the DEIR as a FEMA Federal Staging Area. If the Port relies on emergency response as a principal project purpose or benefit, the EIR and approval record should distinguish that function from scheduled passenger service and visitor-serving development. It should explain how, in response to an emergency, responders, supplies, and passengers would reach the terminal under the flood, seismic, congestion, and road-failure conditions relevant to that claim; identify dependence on the Seaport Boulevard and US 101/Woodside Road corridor and on off-site improvements; and compare the new terminal with existing docking options, including Wharf 5, using evidence about their actual capacity and limitations. (DEIR § 2.2 and Chapter 4.)
The EIR should explain why this new terminal is necessary for infrequent emergency access. Wharf 5 and the other docks shown in the diagram below and as is noted in the Alternatives Analysis, can already provide docking to accommodate a wide variety of water-going vessels, including ferry boats, that would be commandeered in an emergency disaster scenario.
This information bears upon whether the project objectives are stated such that feasible alternatives can be evaluated, and on whether the asserted emergency benefit is supported by a functioning end-to-end access system.
Requested action TR-2. Clarify the emergency function and the assumptions supporting it, evaluate land and water access under relevant disruption scenarios, and compare existing facilities and a limited ferry-focused alternative on a consistent basis.
Diagram of Redwood City Port showing various docking facilities along the shoreline of the deep-water channel
Emergency access
The Port identifies emergency response as a benefit of the proposed ferry service. The DEIR should distinguish the ferry’s potential to move people or supplies by water, when regional roads are disrupted, from the landside access needed to reach the terminal, stage responders or supplies, and continue travel from the terminal. It should state the assumptions and limitations underlying the claimed benefit, including whether the terminal and its landside access would be usable under the disaster scenarios cited in the project objectives. (DEIR Project Description and Objectives; §§ 3.12 and 3.14; Appendix H.)
The project would rely on Seaport Boulevard and the Woodside Road/US 101 interchange for ordinary vehicle access. The FEIR should identify the roadway, interchange, drainage, and power-system assumptions on which its emergency-access analysis relies, and clarify whether the project would improve, worsen, or leave unchanged access under the relevant flood, seismic and other emergency scenarios. This comment concerns the support for the project’s claimed benefit and the adequacy of access to the project site; it does not assume that the project must correct every existing regional roadway vulnerability.
Requested action TR-3. Clarify the scope and limits of the claimed emergency-response benefit, including the landside access and operating assumptions needed to use the terminal during the cited disaster scenarios.
Localized traffic analysis
The DEIR notes Traffic Congestion at the Woodside Road/101 intersection to be “Less than Significant” despite substantial expressed community concerns about peak-hour congestion on Seaport Boulevard and Woodside Road.The transportation analysis should show whether its traffic assumptions capture the concentrated vehicle and shuttle activity associated with ferry arrivals and departures. The FEIR should identify the time intervals used in the analysis and explain whether those intervals can reveal short queues or access conflicts at the terminal, Seaport Boulevard, and the Woodside Road/US 101 interchange. If hourly averages obscure a plausible peak-period queue, then provide a focused shorter-interval analysis, such as 15-minute volumes, for the relevant arrival and departure periods. The FEIR should also identify the approved and reasonably foreseeable projects included in its cumulative scenario, explain their traffic assumptions and route assignments, and address any material omissions. (DEIR § 3.14; Appendix H.)
Requested action TR-4: Identify the temporal resolution and cumulative-project assumptions used in the transportation analysis. If the analysis relies on hourly averages that could mask queues during ferry arrival and departure periods, then provide focused shorter-interval analysis at the affected locations. Identify and correct any material omissions in the cumulative traffic scenario, including approved or reasonably foreseeable projects.
Navigation conflicts and service limits
Redwood Creek serves commercial vessels, marinas, rowing clubs, paddlers, kayakers, and other small craft. The four local rowing clubs report approximately 100 boats launched between 5:30 and 7:30 a.m., with approximately one-third rowed by athletes less than 18 years old.14 At low tides, exposed mudflats narrow the usable waterway and can concentrate small craft in the deeper channel. The DEIR should explain whether these existing uses and tidal conditions were included in the navigation baseline and how they overlap with ferry arrival and departure schedules. (DEIR Chapter 2; §§ 3.3.5.2.1.2, 3.14.)
The project description allows service to expand as demand grows and discusses special-event service. It should define whether private charters, water taxis, or third-party vessels may use the terminal. If those operations are outside the project, the approval and operating agreements should bind the terminal to the fleet, routes, speeds, and service envelope analyzed. If they are reasonably foreseeable, the DEIR should analyze them. The Port should also identify who will monitor compliance with the 7-knot creek limit, how incidents will be recorded, and what required corrective action will follow repeated violations.
Requested action NAV-1. Add a documented baseline of existing waterway uses and tidal constraints, compare those conditions with the analyzed ferry schedule and expansion, and define and enforce the terminal’s operating envelope.
Requested action NAV-2. Clarify how the wake and hydrology modeling account for the cumulative impact of non-WETA vessel traffic operating concurrently with the scheduled 34-knot WETA ferries, particularly during low-tide conditions when the shipping channel narrows significantly.
III. Policy issues that warrant consideration prior to project approval
Failure to consider an Alternative that maximizes sea level rise resilience and makes room for an adaptive response to future conditions is a dire omission
The Project Site, as described in the DEIR, is developed flat land located at the juncture of Redwood Creek and Westpoint Slough. It directly faces Redwood Creek as it passes between Don Edwards San Francisco National Wildlife Refuge’s marshes on Greco Island and Outer Bair Island, connecting with the open waters of San Francisco Bay.
The site presents itself to these marine conditions as the promontory terminus of the Redwood City Seaport. It would be the first land impacted by incoming sea surge produced by extreme storms, seiche waves due to earthquakes, high seas during King Tides, the rise of seas episodically produced by El Nino or Kelvin wave events, as will occur incrementally during sea level rise.
Risk vulnerabilities were noted in San Mateo County’s Sea Level Rise Vulnerability Assessment Final Report of 2018. The Vulnerability Assessment “classified the Port of Redwood City as a Risk Class 3 for buildings and other structures. Under Risk Class 3, the failure of hotels, ports, and roads could pose a substantial risk to human health and has the potential to substantially impact the economy and/or cause mass disruption of daily activity.” (DEIR p.3.9-18)
In light of this high vulnerability, it is inexplicable that the Project did not consider an Alternative that would reduce risks encroaching from the shoreline. The visitor-serving area could be a Resilience Park, perhaps designed as a sloped vegetated ecotone, mitigation for Bay high water and storm-driven inundation, protecting the Ferry terminal and Port lands beyond it. As sea level rise adaptation, its design would take advantage of low-cost nature-based resilience and maintenance while maximizing opportunities for future adaptation as conditions worsen with sea level rise. Please consider that the DEIR discussion recognizes the relevance of SLR adaptation in preparation for impacts of sea level rise and shallow groundwater, existing or upcoming plans and legislation.
While CEQA does not currently require analysis of SLR impacts, State, Regional, County and City jurisdictions have produced studies, ordinances, regional planning guidelines and potential funding opportunities on the subject, many discussed in this DEIR. All such documents are sources that may be taken into consideration in approvals and permitting.
We strongly recommend that the Project include the following SLR and shallow groundwater mitigations.
Expand Setback sufficient to include a SLR levee or adaptive ecotone levee. The setback along Westpoint Slough and Redwood Creek is proposed as 100’ between the shoreline and the foot of the proposed 7’ NFID platform and includes space for a public trail. In Chapter 4 Alternatives Analysis as much as a 110’ setback was suggested. Neither of these widths are sufficient space to include the footprint of an onshore levee for wave run-up protection or a modified levee/ecotone to break up wave action. Given the high risk of the Project location, a minimum of 150’ - 200’ may be required. The 7’ platform would be reduced in horizontal dimensions to accommodate this mitigation.
Monitor shallow groundwater status in shoreline setback and for lower edges of slopes for the NFID 7’ platform, the site access road and the ferry boarding slope.The Project concludes that the 7’ platform of compacted dirt is sufficient mitigation protecting the site from rising groundwater. It makes no analysis of potential shallow and rising groundwater in non-filled areas including shoreline setback, below the lower extent of slopes of the platform, below the lower extent of the access road nor beneath the Ferry boarding slope. As mitigation the shoreline and lower slope areas must (1) be studied using boring techniques to identify existing groundwater conditions prior to fill installation and (2) must include monitoring wells wherever near-surface groundwater is found and require a shallow groundwater monitoring plan.
Port of Redwood City Policy
We are disappointed that neither a Sea Level Rise Policy nor Port-wide SLR or Shallow Groundwater Risk Study is available through this DEIR. As a fully shoreline jurisdiction, all Port operations are highly vulnerable.This finding of the San Mateo County Vulnerability Study was accompanied with only conceptual recommendations for shore protection as it lacked detailed Port shoreline analysis. Prior to all further changes to Port lands, we hope there is a Port policy that investigations should be available, with parcel-specific detail, informing all SLR and shallow groundwater risks along the Port’s shoreline including this Ferry Project.
Make transit service, public costs, and fleet transition transparent
A major public infrastructure investment should be evaluated not only for the impacts of construction, but also for the realistic likelihood that its proposed transportation services, associated public benefits and claimed environmental advantages can be sustained over time.The DEIR uses specified service and ridership assumptions, describes future expansion, and anticipates replacing the Tier 4 renewable-diesel vessels with zero-emission vessels at the end of their useful life. Before approval, the Port and WETA should disclose the fare, subsidy, funding, service phasing, and fleet-transition assumptions that will govern operations. Those commitments matter to the public value of the project and should remain consistent with the service assumptions underlying the DEIR’s ridership, traffic, and emissions analyses.
Please identify the expected fare and subsidy approach, committed service level, funding responsibility, interim emissions reductions, and milestones for fleet transition. Revise environmental assumptions if those commitments differ from the DEIR.
Rezoning may threaten important heavy-industrial uses
The project proposes carving out a new commercial and “visitor-serving” area within the north end of Port's heavy-industrial zone, potentially weakening a zone that is critical for the Peninsula’s economy. The Port of Redwood City is the sole active deepwater port in the South San Francisco Bay. It provides vital maritime infrastructure capable of handling large bulk cargo ships, giving the Mid-Peninsula direct access to domestic and international shipping routes. The vast majority of cargo moving through Redwood City’s heavy industrial zones consists of bulk building materials—primarily sand, gravel, gypsum, concrete aggregate, and liquid asphalt. These materials feed the commercial and residential construction projects keeping the Peninsula's economy growing. This erosion of the unique heavy-industrial zone raises significant concerns regarding the long-term environmental sustainability and compatibility of land use, potentially setting a precedent for future erosion. It is important to note that this visitor-serving hotel and restaurant site adjoins the City’s heavy industry such as the CEMEX cement and gravel and Sims Metals Recycling and the Port itself, creating incompatible land uses. The heavy industry zoning is unique to Redwood City and is critical for the City’s economy as well as for the economy of the entire region of the peninsula.
The Ferry Project presents uncertain prospects as a “Waterfront Economic Engine”
The Ferry operations and terminal is tied to a broader future development of a 9.2-acre parcel, including a planned hotel, restaurants and retail space. For a future “Waterfront Economic Engine”, the Oyster Point Ferry Terminal provides a useful comparison. Under the RM2 mandate, identical to the Redwood City Ferry, the South San Francisco route was legally required to hit a 40% farebox recovery ratio (meaning fares must cover 40% of operating costs). The route has never met this threshold since its inception in 2012, based on an internal study in 2025.15 This remains the lowest-performing route in the entire SF Bay Ferry system (accounting for only 3–5% of overall ferry system traffic and only 1% of commuters to the area). Because of low ridership, the operational subsidy per-passenger translates to roughly $45 to $50+ per single passenger ride, funded by public taxpayers. By comparison, system-wide routes like Oakland/Alameda to San Francisco require under $10 per passenger16. As a result of low ridership, transit officials are currently considering the need for severe service reductions or even possible cancellation17.
The Redwood City Ferry ticket fare compares unfavorably with Caltrain. Caltrain operates a fully electrified fleet from downtown Redwood City to San Francisco. A standard one-way ticket is $6.75. On the ferry, the projected ticket-price is $18.75. For the weekend leisure market, for a family of four, going to a ball game or other event in San Francisco, the transportation cost both ways would be more than $150.00.
With regional transit agencies facing historic structural deficits, committing long-term public subsidies to a low-frequency ferry commuter route requires a more robust justification.
The Port should specifically evaluate how a shortfall in passengers, capital or operating funds could affect the project's projected environmental benefits.
Currently, when State and City goals are focused on urgently reducing climate change, it is unacceptable to plan for diesel ferries. Any approved ferry project should include a binding commitment to purchasing zero-emission ferries if these are available when the terminal is ready for service.18
Thank you for considering these comments.
Respectfully submitted,
Eileen McLaughlin, Board Member
Citizens Committee to Complete the Refuge
Gita Dev, Sustainable Land Use Chair
Sierra Club Loma Prieta Chapter
Jennifer Hetterly, Bay Alive Campaign Coordinator
Sierra Club Loma Prieta Chapter
Chris MacIntosh, Conservation Chair
San Mateo County Bird Alliance
Alexandra Mendoza, Environmental Associate
Green Foothills
1 Renewable diesel (also known as hydrotreated vegetable oil or HVO) is a cleaner-burning, drop-in fuel made from renewable resources like used cooking oil, animal fats, and plant oils, unlike traditional petroleum diesel or “biodiesel”.
2 Ferry Terminal Draft EIR, Appendix E, Geotechnical Desktop Study, COWI, 2024
3 Ibid., 13
4 Ibid., 22
5 Ibid., 24
6 Haley and Aldrich, 2024. Results of Chemical, Physical and Biological Testing of Sediments, Wharves and Multi-Use Basin, Port of Redwood City.
7 DTSC, 2022. IN THE MATTER OF: ENFORCEMENT ORDER FOR CORRECTIVE ACTION, SIMS METAL MANAGEMENT, 699 SEAPORT BOULEVARD, REDWOOD CITY, CA 94063 (Docket No. HWCA-FY20/21-003; ENFORCEMENT ORDER)
8 https://abc7news.com/post/crews-battling-large-fire-sending-off-huge-plume/14859040/
10 Port of Redwood City 2020 Vision Plan, p. 12: https://782212a8-b0fc-46e8-958b-591493c263bd.filesusr.com/ugd/9d6aca_1311cb4ffeac432fb03892fc82cb0ed1.pdf
11 CEQA Guidelines, 15003 (c),(d): https://www.califaep.org/docs/CEQA_Handbook_2026_rev031926_Updated.pdf
12 San Mateo County, Environmental Justice Communities Technical Appendix, Public Draft, February 2025, pp. 3, 8–11.
13 BCDC-SAN FRANCISCO BAY ECOLOGY AND RELATED HABITATS, Staff Report, 2002
14 Based on informal communication with BIAC
15 South San Francisco Ferry Service Study July 23, 2025
16 SF Chronicle, March 17, 2013, South San Francisco ferry loaded with subsidies
17 South San Francisco Ferry Service Study July 23, 2025
18 However, if a renewable diesel fleet is finally approved for initial operations, the FEIR should enforce a binding mitigation measure requiring a phased transition to hybrid or all-electric propulsion systems by, and preferably well before, the 25-year mark.